Part of the overall project governance is the Change
Control. This can refer to changes in
the scope of the project, the budget, the Schedule, the services provided or
the products the project produces.
Change control needs to be in place to ensure that the project is
delivered on time, to budget and delivers the required product. Change control ensure that any change
introduced to the project is defined.
Change can be introduced into the project and will be
introduced into the majority of projects.
The world would be great if people did not change their minds, but this
simply does not happen in the real world.
Change needs to be introduced in a controlled manner, hence
we use the term “Change Control”. A
formal process of submission, review, acceptance and implementation must be
followed and documented to ensure all stakeholders understand the change and
what it will mean for the project.
Any member of the Project Team, or Stakeholder should be
able to request a change and the process begins with the Change Request. A document with a small number of mandatory
pieces of information is required. This
does not need to be excessive, however it needs to cover all of the information
that a Project Manager and the Stakeholders need to be able to make an informed
decision to continue.
The Change Request will include the following information;
Requester, Description of change, Type of Change (budget, scope , schedule), Benefits
of the change, Estimated Costs, Impacts of the change and the expected
Deliverables of the change.
Once the change has been submitted, the Change Manager, or
Project Manager in most projects, would accept the Change Request for review and
assess the requirement. A feasibility
study maybe required for large requests to understand the impact to the project
and to obtain acceptance of the requirements.
The Change Request details will be recorded into a Change Log.
Once the Change Request has been accepted and assessed, it will
then be presented to the Change Board.
The Change Board will decide with a conscious to accept the change or
discard it for rejection. The Change Log
will be updated to reflect the decision.
Once the change is approved, the Project Manager will
identify all of the aspects that are impacted within the project, such as
schedules and costs. The Project Plan
will be updated to include the change and work packages will be created,
assigned and executed. The Change
Requestor will be informed that their request has been accepted.
Once the change has been implemented into the project, the
Change Request can be updated to a status of complete and the original Change
Requester will be informed. The Change
Log will be updated to complete and close the Change Request.
The change process is very simple, but is easily over
looked. A Project Manager must ensure
that the Change Control Process is defined in the Project Plan, or even a
separate document. A Change Log should
be created to record all requests and the status of each and a Change Request
Template should be created, so that all changes can be recorded with a standard
document.
No comments:
Post a Comment